The deck ties the arch ends together, so foundations carry mainly vertical load.

本页面尚未提供简体中文版本,现显示英文版。

示意图:Tied arch pedestrian bridges
示意图,并非已完工项目的照片。

In a tied arch the horizontal thrust of the arch is resisted by a tie, usually the deck edge girder. This makes the arch form possible on sites where foundations cannot take large horizontal forces.

Typical considerations

  • Hanger arrangement and adjustability.
  • Shallow structural depth below the deck, which helps with clearances.
  • Lifting the completed span or erecting it on temporary supports.

Final member sizes, details and specifications are determined by the engineer of record for each project. This page describes general practice and does not replace project-specific engineering.

本内容为一般性技术信息,不能替代针对具体项目的结构设计。结构设计必须由合格工程师依据适用规范和主管部门的要求完成或批准。